Construction Accidents plaguing the Wicomico River

Kathy Phillips's picture

A construction accident at the Salisbury, MD wastewater treatment Plant on Feb. 7 resulted in a reported 5,000 gallons of partially treated sewage being discharged into the Wicomico River through an on-site storm drain that feeds directly into the river.

On March 26 another construction accident while installing plant upgrades dumped an estimated 28,000 gallons or more of sewage into the river through the same storm drain.